Power lines and the grid

Why new high-voltage lines and substations are being proposed, where they could run, and how much say the county has.

Why this matters to students

The transmission lines planned today will cross the roads you drive, the parks you visit and the places you might someday live. Who pays to expand the grid also affects every household's electric bill.

The question

Who decides where new transmission lines and substations go, and what can Loudoun residents do about it?

Background in two minutes

Most new power demand in Northern Virginia comes from data centers, and moving that much electricity takes high-voltage transmission lines and substations. Utilities such as Dominion Energy and private developers propose the projects.

The county's power over them is split. Transmission lines are approved by Virginia's State Corporation Commission (SCC), not the county, so the Board can only take positions and testify. Substations on private land, however, need a county special exception, which means the Board can approve or deny them.

The case for building new lines

Utilities and grid planners say demand is growing fast and the grid needs new capacity to stay reliable for homes, hospitals and businesses as well as data centers.

The county itself has supported some projects when they use corridors that already exist. In 2025 the Board backed Dominion's Morrisville to Wishing Star line on the condition that it stay in an existing right-of-way rather than cut through neighborhoods.

The case against new routes

Opponents argue that new routes through western Loudoun would damage rural landscapes, farms and historic areas, and the Board has formally opposed both the NextEra 500-kV route and the Valley Link 765-kV line on those grounds.

Others question whether every project is really about reliability. When the Board denied the Tech Park at Dulles substation in 2026, the county said it was not a grid reliability project and would mainly attract new high-wattage users that would require even more lines.

What the county actually did

Because the SCC has the final say on lines, most of the Board's actions are positions and filings. Its direct power shows up in substation decisions.

Open questions

  • What route will Valley Link propose when it files with the SCC, expected in 2027, and will the county testify?
  • Will the proposed pause on substation applications pass on Oct. 20, 2026?
  • What substation standards will Phase 2 of the data center rules include?